题目内容:
Scope changes on projects are inevitable.However, scope changes can be minimized by:( )A.Effective implementation of the scope management processes
B.Spending more time analyzing where the estimates came from and who did the estimating
C.Asking the sponsor to supervise all of the planning
D.Developing a detailed Project Charter A.有效完成范围管理过程
B.花更多时间分析估算是怎样得出的及是谁做估算
C.请求业主监督规划的所有事项
D.制定详尽的项目章程
参考答案:
答案解析: