单选题:Increasing resources on the critical path activities may not

  • 题目分类:PMP
  • 题目类型:单选题
  • 查看权限:VIP
题目内容:
Increasing resources on the critical path activities may not always shorten the length of the project because:( )
A.No activities are time-dependent or resource-dependent
B.Activities are always scheduled with optimal number of resources
C.The Project Manager always selects original resources with the highest skill levels
D.Adding more resources may create additional work and produce inefficiencies A.没有活动是依赖时间或依赖资源的
B.总是以最佳的资源数量来安排活动
C.项目经理总选择具有最高技能水平的初始资源
D.增加更多的资源可能产生额外的工作并且导致效率低
参考答案:
答案解析:

A project manager sends the electrical engineer an e-mail me

A project manager sends the electrical engineer an e-mail message asking her to

查看答案

All of the following customer expectations are driving compa

All of the following customer expectations are driving companies to adopt a qual

查看答案

Complete inspection for the products of a project:( )A.Is an

Complete inspection for the products of a project:( )A.Is an appropriate way to

查看答案

For the following group of numbers: 80, 10, 10, 50, 70 and 9

For the following group of numbers: 80, 10, 10, 50, 70 and 90 what is the mode?(

查看答案

Directions: This part consists of a short passage. In this p

Directions: This part consists of a short passage. In this passage, there are al

查看答案