A project manager sends the electrical engineer an e-mail message asking her to prepare a detailed technical report per some instructions given in the e-mail.A week later, the electrical engineer’s department manager visits the project manager to complain that his engineer had spent 45 hours preparing the 80-page report.The project manager indicates that he thought the report would be only 4 pages long.The problem here is one of: ( )A.Lack of feedback
B.Too many instructions C.Too much communication
D.Lack of trust ( ) A.缺乏反馈
B.指令太多
C.沟通太多
D.缺乏信任