题目内容:
Aprojectmanagerhastheoptionofproposingasystemstoaclient:thatsatisfiestheminimumrequirementsplushasafewextrafeatures(the"Toyota").Theon-timerecordsis:OnTimeProb=90%,profit=$50,000;LateProb=10%,profit=-$10,000.Whatistheexpectedmonetaryvalueofthe"Toyota"system?( )
A.$9,900
B.$44,000
C.$45,000
D.$48,000 A.9,900美元
B.44,000美元
C.45,000美元
D.48,000美元
参考答案:
答案解析: