题目内容:
A project manager estimates a project will take 14 weeks at a cost of $60,000.In signing the contract documents, the customer imposes a penalty for late completion of $2,000 per estimates that the maximum possible crashing of the project duration is 4 weeks, at an additional cost of $9,000.Assuming that the project manager is going to make the decision and that cost is the driving criteria for the project manager’s organization, what is the expected project cost? ( )A.$69,000
B.$71,000
C.$70,000
D.$62,000 A.$69,000
B.$71,000
C.$70,000
D.$62,000
参考答案:
答案解析: