题目内容:
You have been assigned as a project leader and must first review the statement of work provided by the customer.Although the answer can vary based on the industry, choose which one of the following are you most likely to overlook?( )A.Data item deliverables
B.Customer-furnished equipment and facilities
C.Long-lead procurement items
D.Customer-imposed milestones A.工作成果数字化
B.客户提供的设施
C.长期重要的采购内容
D.客户要求的工作里程碑
参考答案:
答案解析: