题目内容:
To further ensure that the work outputs of the project are accepted by the customer, the project team should:( )A.Change the project scope when requested by the customer
B.Follow a scope verification process
C.Modify the project plan and baseline as needed.
D.Use a PERT Chart A.当客户要求时,变更项目范围
B.遵循范围确证过程
C.根据需要调整项目计划和基准
D.利用计划评审技术PERT图
参考答案:
答案解析: