单选题:How do the project manager and the project team select which

  • 题目分类:PMP
  • 题目类型:单选题
  • 查看权限:VIP
题目内容:
How do the project manager and the project team select which communications technology to use to transfer information among project stakeholders? ( )
A.They analyze the team member ’s experience and expertise
B.They determine the critical path for the project
C.They don’t analyze the anticipated project environment
D.They determine if they are on track using earned value A.他们分析团队成员的经验和专长
B.他们决定项目的关键路线
C.他们不分析所预料到的项目环境
D.使用挣值分析, 他们决定是否进展顺利
参考答案:
答案解析:

两个以上的物品环绕一个中心组合在一起,两边平衡、重量或吸引力(包括形状、色彩方面的吸引力)都有同等的分量,使人产生一种宁

两个以上的物品环绕一个中心组合在一起,两边平衡、重量或吸引力(包括形状、色彩方面的吸引力)都有同等的分量,使人产生一种宁静的感觉,这就叫做均衡。根据定义,下列不

查看答案

Which of the following is not an external, unpredictable ris

Which of the following is not an external, unpredictable risk? ( )A.Changes in g

查看答案

The requirements and functional specifications have been com

The requirements and functional specifications have been completed and the accep

查看答案

Your project experiences an internal failure of a major comp

Your project experiences an internal failure of a major component causing projec

查看答案

The document that describes the end use of an item and that

The document that describes the end use of an item and that is used to stimulate

查看答案