How do the project manager and the project team select which communications technology to use to transfer information among project stakeholders? ( )A.They analyze the team member ’s experience and expertise
B.They determine the critical path for the project
C.They don’t analyze the anticipated project environment
D.They determine if they are on track using earned value A.他们分析团队成员的经验和专长
B.他们决定项目的关键路线
C.他们不分析所预料到的项目环境
D.使用挣值分析, 他们决定是否进展顺利