题目内容:
In order to manage a project effectively, work should be broken down into small pieces.Which of the following does NOT describe how far each task should be broken down?( )A.Can be completed in under 80 hours
B.Can not be logically subdivided further
C.Is done by one person
D.Can be realistically estimated A.可以在80小时以下完成。
B.不能再进一步进行逻辑细分了。
C.可由一个人完成。
D.可以进行实际估算。
参考答案:
答案解析: