单选题:A line manager possesses information, which the project team

  • 题目分类:PMP
  • 题目类型:单选题
  • 查看权限:VIP
题目内容:
A line manager possesses information, which the project team needs, but withholds the information.This is a type of: ( )
A.Confrontation
B.Information filtering
C.Region of influence
D.Communication power base A.正面对抗
B.信息过滤
C.影响区域
D.基本沟通力
参考答案:
答案解析:

The expected value of a risk event is calculated by multiply

The expected value of a risk event is calculated by multiplying the . ( )A.Likel

查看答案

Which of the following utility functions reflect risk aversi

Which of the following utility functions reflect risk aversion? ( )A.Uniform B.I

查看答案

Which of the following statements best describes attribute s

Which of the following statements best describes attribute sampling?( )A.Is expr

查看答案

Which of the following is not a type of contract modificatio

Which of the following is not a type of contract modification?( )A.Termination B

查看答案

The relationship of specific procurement actions to the proj

The relationship of specific procurement actions to the project strategy is call

查看答案