题目内容:
Customer is requiring scope changes.In order to analyze the influences to the project, PM should review WBS, change request, scope management plan and – ( )A.Performance Report
B.RAM
C.Pareto Diagram
D.Monte Calro Simulation A.绩效报告
B.职责分配矩阵
C.帕累托图
D.蒙特卡洛模拟
参考答案:
答案解析: