Upon completion of the plan, your team determines that the schedule developed is too long.An analysis shows that the network diagram cannot be changed.You have additional resources available and some work can be easily shared with additional resources.Your best approach would be to:( )A.Fast track the project
B.Conduct a Monte Carlo analysis
C.Use a parametric estimate
D.Crash the schedule A.快速追踪项目
B.引导一项 Monte Carlo 分析
C.利用参数估算
D.赶工进度