题目内容:
Which of the following does not represent the critical path?( )A.Has a high degree of risk
B.Will elongate the project if the activities on this path take longer than anticipated
C.Must remain on schedule
D.Has the largest number of activities of any path A.有高度风险
B.如果这条路线上的活动要比所预期的花更长时间,项目时间将延长
C.必须保持按进度
D.任何有最大数目活动的路线
参考答案:
答案解析: