单选题:Project managers will often encounter barriers to building e

  • 题目分类:PMP
  • 题目类型:单选题
  • 查看权限:VIP
题目内容:
Project managers will often encounter barriers to building effective project teams.To avoid the conflicts associated with the assignment of project roles and responsibilities, the project manager should: ( )
A.Develop a Responsibility Assignment Matrix with the project team
B.Avoid sharing of work package details between functional groups
C.Monitor the team activities closely
D.Personally direct the team’s work activities A.设计一个项目团队责任分配矩阵
B.职能小组之间避免分享详细工作情况
C.严密监控团队活动
D.亲自指导团队的工作活动
参考答案:
答案解析:

Thethreemostcommontechniquesfordevelopingprojectcostestimate

Thethreemostcommontechniquesfordevelopingprojectcostestimatesare:( )A.Budgetary,

查看答案

Usingthetablebelow,thelaborratecostvarianceis:( )A.$68,329.0

Usingthetablebelow,thelaborratecostvarianceis:( )A.$68,329.00B.$386.00C.($0.22)D

查看答案

Once the logic of a network is laid out, the project manager

Once the logic of a network is laid out, the project manager will conduct a forw

查看答案

In the Arrow Diagram Method (ADM), the project element, whic

In the Arrow Diagram Method (ADM), the project element, which lies between two e

查看答案

In a start-to-start relationship between two tasks not on th

In a start-to-start relationship between two tasks not on the critical path, the

查看答案