承包人提出的工程变更,应当提交(  )审查并批准。

承包人提出的工程变更,应当提交(  )审查并批准。A.发包人 B.设计方 C.发包人和设计方 D.工程师

查看答案

工程具备隐蔽条件或达到专用条款约定的中间验收部位,承包人进行自检,并在隐蔽或中间验收前最晚(  )小时书面形式通知工程师

工程具备隐蔽条件或达到专用条款约定的中间验收部位,承包人进行自检,并在隐蔽或中间验收前最晚(  )小时书面形式通知工程师验收。A.12 B.24 C.36 D.

查看答案