In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communications. According to Metcalfe's Law, a project with 10 stakeholders has__________ potential communication channels.
A.
10 B. 45
C. 50
D. I00