Whichofthefollowingwouldnotnecessarilyincreasetheaccuracyofestimatingtheprojectcost?( )
A.Pricingouttheworkatlowerlevelsintheworkbreakdownstructure
B.Usinghistoricaldata
C.Talkingtopeoplewhohaveworkedonsimilarproject
D.Spendingadditionaltimeontheestimate A.在工作分解结构中,在较低的水平订定工作价格
B.使用历史数据
C.与有类似项目工作经验的人进行交流
D.花额外的时间进行估算
参考答案:
答案解析:

Thetechniquescommonlyusedtodeterminetheprofitabilityofaproje

Thetechniquescommonlyusedtodeterminetheprofitabilityofaprojectincludeallofthefol

查看答案

In some Arrow Diagramming Method (ADM) networks, the project

In some Arrow Diagramming Method (ADM) networks, the project manager may be requ

查看答案

Among the common types of scheduling techniques, task relati

Among the common types of scheduling techniques, task relationships are best ill

查看答案

For every project situation, several methods usually exist f

For every project situation, several methods usually exist for effective communi

查看答案

新华书店出售儿童读物,上午进货量为总数的28%,下午出货量为目前总量的25%,晚上进货量为目前总量的50%,如原有读物2

新华书店出售儿童读物,上午进货量为总数的28%,下午出货量为目前总量的25%,晚上进货量为目前总量的50%,如原有读物200本,则晚上进货后有(  )本。A.2

查看答案