Many useful tools and techniques are used in developing schedule._____(72)_____ is aschedule network analysis technique that modifies the projectschedule to account for limited resource.
(72)A. PERT
B.Resource levelling
C.Schedule compression
D.Criticalchain method
参考答案:
答案解析: