When evaluating the possible solutions and tradeoffs to resolve a project conflict, the project conflict, the project manager should: ( )
A.Consider only lessons learned from previous projects
B.Ignore the potential of compromising the sponsor’s objectives, and corporate strategic plan
C.Fully consider possible impact on schedule, cost, risk, and performance
D.Consider only the effect on resources consumed and project resource consumption for that project A.只考虑以前项目的经验教训
B.不考虑是否有协调业主的目标与公司的策略计划的可能性
C.完全充分考虑到对进度,成本风险和绩效的影响
D.只考虑对所用资源的影响及该项目的整个资源消耗情况
参考答案:
答案解析:

Project risk management can be defined as the process necess

Project risk management can be defined as the process necessary to identify, ana

查看答案

一条街上,一个骑车人与一个步行人同向而行,骑车人的速度是步行人速度的3倍,每隔10分钟有一辆公共汽车超过行人,每隔20分

一条街上,一个骑车人与一个步行人同向而行,骑车人的速度是步行人速度的3倍,每隔10分钟有一辆公共汽车超过行人,每隔20分钟有一辆公共汽车超过骑车人。如果公共汽车

查看答案

Which of the following is not part of the generally accepted

Which of the following is not part of the generally accepted view of quality tod

查看答案

In which type of contract arrangement is the customer at gre

In which type of contract arrangement is the customer at greatest risk of absorb

查看答案

Discussion--about 5 minutes In this part of the test the exa

Discussion--about 5 minutes In this part of the test the examiner reads out a sc

查看答案