Inputs to activity duration estimating include all of the following except:( ) A.Expert judgment B.Constraints C.Assumptions D.Resource capabilities
A.专家判断 B.限制因素 C.假定 D.资源能力
参考答案:
答案解析:
When the risk event probabilities are multiplied by their re
When the risk event probabilities are multiplied by their respective estimated r