During project execution the project manager and project team will experience performance variances and be required to take corrective actions.These corrective actions may be of assistance to other project managers and should be shared and documented through a: ( )A.Change control board
B.Steering committee
C.Quantitative risk analysis
D.Lessons learned process A.变更控制委员会
B.指导委员会
C.定量风险分析
D.经验教训学习过程