题目内容:
Which of the following would you do if you wanted the contractor to start work on a project immediately?( )A.Issue a letter contract, but follow up as soon as possible with some type of a final contract
B.Sign a Time and Materials contract for the entire effort
C.Negotiate a Firm Fixed Price contract
D.Negotiate a cost sharing arrangement A.先签发一封合同意向书,然后尽快形成某种类型的最终合同书
B.对整个任务工作,签一份个工时和原材料合同
C.谈判达成实盘固定价合同
D.谈判达成成本分摊办法
参考答案:
答案解析: