A project schedule whose start and finish dates reflect expected resource availability is called:( )A.Resource limited schedule
B.Resource partitioning schedule
C.Resource leveling schedule
D.Resource quantification schedule A.资源限制的进度
B.资源分配进度
C.资源平衡进度
D.资源定量化进度