Precedence Diagramming Method(PDM)is a method used in activity sequencin9.There are four types of dependencies or precedence relationships in PDM.The initiation of the successor activity depends upon the completion of the predecessor activity is called __________ .
A.
Finisto—Start B. Finisto—Finish
C. StartStart
D. StartFinish