单选题:Thescopeofaprojectcanbeexpectedtochangeif:( )A.Theprojectman

  • 题目分类:PMP
  • 题目类型:单选题
  • 查看权限:VIP
题目内容:
Thescopeofaprojectcanbeexpectedtochangeif:( )
A.Theprojectmanagermustprovidecostestimateswithouthavingadesignconcept
B.Oversimplification(underestimating)ofthenatureoftheworkoccurs
C.Theprojectmanagerisassignedaftertheprojectisdefined,andthecostandscheduleareapproved
D.Alloftheabove A.项目经理提供了没有设计概念的成本评估
B.低估了工作产生的结果
C.项目经理在项目已经被定义,成本和进度已经被批准后被指派
D.以上都是
参考答案:
答案解析:

Projectsareparticularlysusceptibletoriskbecause—( )A.Murphy’

Projectsareparticularlysusceptibletoriskbecause—( )A.Murphy’slawstatesthat"ifsom

查看答案

某律师同为甲、乙两公司的常年法律顾问,而且在其顾问服务项目中均包括诉讼案件的代理,现甲、乙两公司之间因合同发生纠纷起诉至

某律师同为甲、乙两公司的常年法律顾问,而且在其顾问服务项目中均包括诉讼案件的代理,现甲、乙两公司之间因合同发生纠纷起诉至法院,两公司均要求该律师担任其代理律师。

查看答案

Scope changes on projects are inevitable.However, scope chan

Scope changes on projects are inevitable.However, scope changes can be minimized

查看答案

Adetailedprojectschedulecanbecreatedonlyafter?( )A.Aprojectp

Adetailedprojectschedulecanbecreatedonlyafter?( )A.Aprojectplaniscreated. B.AWBS

查看答案

The most encompassing document to help the project team with

The most encompassing document to help the project team with project integration

查看答案