In making key changes to a project, it is important to have a formal change process and a ____________ responsible for approving or rejecting requests. ( )A.Stakeholder
B.Change control board
C.Subject matter expert
D.Project manager A.项目相关者
B.变更控制委员会
C.领域事务专家
D.项目经理