单选题:已知某钢筋工程每周计划完成的工程量和第l—4周实际完成的工程量见下表,则截止第4周末工程实际进展点落在计划S曲线的(  

题目内容:
已知某钢筋工程每周计划完成的工程量和第l—4周实际完成的工程量见下表,则截止第4周末工程实际进展点落在计划S曲线的(  )。
A.右侧,表明此时实际进度比计划进度拖后50t
B.右侧,表明此时实际进度比计划进度超前80t
C.左侧,表明此时实际进度比计划进度超前60t
D.左侧,表明此时实际进度比计划进度拖后80t

参考答案:
答案解析: