题目内容:
Project managers normally manage to the third level of the WBS.Managing at this level allows the project manager to:( )A.Supervise all technical work
B.Control the work package elements
C.Exercise his or her technical expertise
D.Maintain better control of integrated efforts A.监督所有技术工作
B.控制工作模块要素
C.发挥自己的技术专长
D.更好地保持控制整合工作
参考答案:
答案解析: